July 1 Medical Office Building Updates

7/1/2021
At the new medical office building site, workers are welding bracing to the beams and detailing. A crew is finishing the column and beam framing on the east portion, and the concrete crew has formed the remaining foundation wall for the building.

The new meeting room will be open before long but without flooring. Carpet will be installed at a later date.

Electricians installed under-slab conduit, plumbers are installing waste and vent piping, and the KBC crew has installed storm piping and a catch basin in the parking lot extension at our Orthopaedic & Rehab building.
 
Sort by: Name Date Size
131545428_45168...
Size: 1.1 MB
Uploaded: 6/25/2021
198618221_45168...
Size: 1.2 MB
Uploaded: 6/25/2021
198899815_45168...
Size: 670 kB
Uploaded: 6/25/2021
199533197_45168...
Size: 1.1 MB
Uploaded: 6/25/2021
201800015_45168...
Size: 938 kB
Uploaded: 6/25/2021
204651741_45168...
Size: 1.1 MB
Uploaded: 6/25/2021
204660353_45168...
Size: 650 kB
Uploaded: 6/25/2021
Wabash General Hospital logo
Back to top